July 23, 2023 - Quezon City

Maintenance Schedule

BETWEEN 9:30AM AND 2:30PM – PORTION OF CIRCUIT MARIKINA 41VG
Portion of Rivera St. from Col. Bonny Serrano Ave. to 4th St. in St. Ignatius Village, Bgy. St. Ignatius.
Portion of Rivera St. from Astoria St. to and including 3rd, 4th, Jamaica and Woodside Sts. in St. Ignatius Village, Bgy. St. Ignatius.

BETWEEN 2:15PM AND 2:30PM – THE WHOLE OF CIRCUIT CUBAO 434VQ
Portion of 13th Ave. from Meralco – Cubao substation to Col. Bonny Serrano Ave. in Bgy. Socorro, Cubao.
Ali Mall along P. Tuazon Blvd. in Bgy. Socorro, Cubao.

Reason

Line reconstruction works, line reconductoring works and installation of facilities along Col. Bonny Serrano Ave. corner Rivera St. in St. Ignatius Village, Bgy. St. Ignatius, Quezon City.