January 8, 2023 - Cavite (Noveleta, Rosario and Cavite City)

Maintenance Schedule

BETWEEN 3:00AM AND 3:59AM AND THEN BETWEEN 8:01PM AND 9:00PM - THE WHOLE OF CIRCUITS ROSARIO 42RS AND 43RS

Portion of Gen. Trias Drive and Marseilla St. from Meralco – Rosario substation to Manila – Cavite Road including the whole town of Rosario.

Portion of Manila – Cavite Road from Marseilla St. to and including the whole of Cavite City; Bgys. Magdiwang, Salcedo I & II, San Juan I, San Rafael I – IV and Poblacion in Noveleta.

BETWEEN 10:00AM AND 8:00PM – PORTION OF CIRCUIT ROSARIO 43RS

Portion of Marseilla St. from Manila – Cavite Road to and including Bgys. Salcedo I and II in Noveleta.

Portion of Marseilla St. from Gen. Trias Drive to and including Bgys. Bagbag I & II, Ligtong I, II & III and Silangan I & II in Rosario.

Portion of Gen. Trias Drive from Meralco – Rosario substation to Bgy. Poblacion including Bgys. Wawa III and Tejeros Convention in Rosario.

Reason

NGCP preventive maintenance and testing works inside NGCP Rosario - substation.