Distributed Energy Resources
SGF Zero Export Solar System
Under the latest DOE policy, DOE DC 2026-08-0017, customers are now allowed to install and operate a Self-Generating Facility Zero-Export Solar System (SGF ZESS) for their own-use electricity generation, subject to the policy's requirements.
SGF ZESS allows customers to generate electricity for their own use through a solar PV system without exporting electricity to the distribution system. Depending on how the system is configured, it may either operate alongside the customer's Meralco service or independently from it.
To help provide customers with clear and consistent information, these FAQs cover the key points customers may need to know about SGF ZESS, including system configurations, notification requirements, permits, and installation-related concerns.
SGF Zero Export Solar System FAQs
-
1
What is an SGF Zero-Export Solar System, and are there different types?
A Self-Generating Facility Zero-Export Solar System (SGF ZESS) is a solar PV system that generates electricity for customers' own use without exporting electricity to the distribution system.
There are two types:
- Connected SGF ZESS – operates alongside your Meralco service, with controls that prevent excess electricity from flowing to the grid.
- Isolated SGF ZESS – operates independently, with no connection to your Meralco-served electrical system.
-
2
How do I know which system type I have?
It depends on whether your solar system is connected to Meralco's power supply.
- Connected SGF ZESS: Your solar system is connected to Meralco's power supply. During a power outage, it automatically disconnects from Meralco's power supply for safety. If you have a battery system, your system may keep running even after disconnection through an isolator switch.
- Isolated SGF ZESS: Your solar system has no connection to Meralco's power supply at all.
-
3
Do I need to notify Meralco of my SGF ZESS?
It depends on your system type:
Connected SGF ZESS – Yes, you need to notify Meralco after installation so we can update our records. Submit your Notification Form through any of the following channels:
- Online via MS forms here; or
- Download and submit the accomplished Notification Form via:
- any Meralco Business Center; or
- email: customercare@meralco.com.ph with subject line: Own-Use Notification - [Customer Full Name] - [CAN]
Please submit your notification through only one channel. Meralco will process it once the form and required details are complete.
- Isolated SGF ZESS – No, you do not need to notify Meralco.
-
4
What permits are required for an SGF ZESS?
Apart from the requirement of notifying Meralco of your Connected SGF ZESS, both Connected and Isolated SGF ZESS system types require a Building Permit which you must obtain from your city or municipality.
An ERC Certificate of Compliance (COC) is also required for both system types, except for households, clinics, hospitals, and other medical facilities, which are exempt from this requirement.
Please take note that your SGF ZESS solar PV installation must comply with the Philippine Electrical Code and all applicable technical, product-quality, and safety standards.
-
5
Is a Distribution Impact Study required before installation?
No. A Distribution Impact Study (DIS) is not required to install a Connected SGF ZESS.
After you notify Meralco of your installation, we may conduct a DIS at our own cost for system planning and safety purposes. This will not delay or prevent installation. Meralco may also contact you if additional information is needed for planning, safety validation, or investigation of identified irregularities.
-
6
Does a connected SGF ZESS need a protective device to prevent export?
Yes, a connected SGF ZESS must have functional control or isolation mechanisms such as reverse power protection, a limiter, and similar devices to prevent inadvertent export – helping protect you from unexpected charges on your electricity bill and safeguarding Meralco's distribution system.
-
7
Do I need to replace my existing meter?
No, there is no requirement to replace your existing meter if you are an SGF ZESS customer.
Micro Solar System
Under the latest DOE policy, DOE DC 2026-08-0017, the availability of Micro-Solar Systems (MSS) gives customers another option for generating electricity from solar power for their own use. These plug-and-play systems are designed to be connected to the customer's electrical system and operate alongside their Meralco service.
Under the policy, MSS is subject to specific requirements on system capacity, equipment, safety, and customer notification. While an MSS does not require a Building Permit or an ERC Certificate of Compliance, customers are still expected to ensure that their system meets applicable electrical and safety standards.
These FAQs provide guidance on the key considerations for customers who have installed or are planning to install an MSS, including system requirements, notification to Meralco, possible bill savings, treatment of excess electricity, and meter replacement.
Micro Solar System FAQs
-
1
What is a Micro-Solar System?
A Micro-Solar System (MSS) is a plug-and-play solar PV system designed for your own electricity use. To qualify as an MSS, it must have:
- Up to 1 kW DC total solar PV capacity
- A grid-tied micro-inverter with a maximum output of 800 W
- A factory-set, grid-tied micro-inverter with automatic anti-islanding protection
- A Philippine Electrical Code-compliant plug
-
2
Do I need to notify Meralco of my MSS?
Yes. As prescribed by the latest DOE policy (2026-08-0017), you need to notify Meralco after installing an MSS because it is connected to your electrical system. If you have an analog meter, Meralco will replace it with a suitable meter for MSS within 12 months from the date of your notification. Since an MSS may occasionally export excess electricity, this will prevent unexpected charges in your bill.
-
3
How do I notify Meralco of my MSS?
Submit your Notification Form through any of the following channels:
- Online via MS forms here; or
- Download and submit the accomplished Notification Form via:
- any Meralco Business Center; or
- email: customercare@meralco.com.ph with subject line: Own-Use Notification - [Customer Full Name] - [CAN]
Please submit your notification through only one channel. Meralco will process it once the form and required details are complete.
-
4
Do I need a Building Permit or ERC Certificate of Compliance?
No, an MSS does not require a Building Permit or ERC Certificate of Compliance (COC).
However, it must still comply with the Philippine Electrical Code and all applicable technical, product-quality, and safety standards.
-
5
Can an MSS earn bill credits?
To earn credits for exported electricity, you must separately apply for Net-Metering and execute a Net-Metering Agreement with Meralco.
-
6
Do I need to replace my existing meter?
If you have an analog meter, it may be used for up to 12 months after notifying Meralco of your MSS. Within this period, Meralco will replace it with a meter suitable for MSS.
Any meter replacement cost will follow applicable ERC regulations.
Distributed Energy Resources (DER) Overview
For customer-owned, non-exporting solar systems, use the SGF Zero Export and Micro Solar System guidance above. The DER Rules below cover exporting installations and end-user-consumption installations whose owner and end-user are different entities.
Distributed Energy Resources (DER) are power sources connected to the distribution system or electrical system of end-users that could be aggregated to meet demand for energy.
On 29 November 2022, the Energy Regulatory Commission (ERC) Resolution No. 11, Series of 2022, “A Resolution Adopting the Rules Governing Distributed Energy Sources (DER)” also known as the “DER Rules”, was published in a newspaper of national circulation and took effect on 14 December 2022.
The DER Rules cover three (3) types of installations:
- DERs utilizing renewable energy (RE) sources for end-user systems connected on-grid and are meant for consumption and export, with nameplate capacity* of greater than 100kW up to 1MW, but maximum capacity to export capped at 30%;
- DERs utilizing renewable energy (RE) sources for end-user systems connected off-grid and are meant for consumption and export, with nameplate capacity not greater than 1MW, and maximum capacity to export also capped at 30%; and
- DERs utilizing any energy generation and storage technology, whether on- or off- grid, and meant for end-user consumption only, so long as the DER owner and end-user are not the same entity.
Technologies such as microgrids, electric vehicles (EVs), Net-metering, stand-alone battery energy storage systems, etc. that are covered by other regulations are not covered by the DER Rules.
*Nameplate capacity refers to the maximum rated output of an electric power equipment
Compensation Methodology for DER Export Energy
For on-grid Renewable DER, the DU will compensate the exported energy based on the DU’s monthly blended generation rate, in relation to its DER’s rated capacity, computed as follows:
- a. 100kW to 500kW: 75% of the blended generation rate
- b. Above 500kW to 1MW: 60% of the blended generation rate
Eligibility to Join the DER Program
All customers with good credit standing in the payment of their electric bills and new customers are qualified provided the DER system falls under any of these types:
- DERs utilizing renewable energy (RE) sources for end-user systems connected on-grid and are meant for consumption and export, with nameplate capacity of greater than 100kW up to 1MW;
- DERs utilizing renewable energy (RE) sources for end-user systems connected off-grid and are meant for consumption and export, with nameplate capacity not greater than 1MW; and
- DERs utilizing any energy generation and storage technology, whether on- or off- grid, and meant for end-user consumption only, so long as the DER owner and end-user are not the same entity.
DER Application and Installation Process
For end-user consumption and exporting Renewable DER, upon completion of all documentary requirements, payment of the fees, installation of all necessary electrical assets, and securing of all the certificates and permits Meralco will then replace the existing meter with a bi-directional meter, install a REC meter, and do testing and commissioning activities of the RE system. Upon release of the Certificate of Compliance (COC) with the Energy Regulatory Commission (ERC) will you then be able to safely use and benefit from your DER installation.
For purely end-user consumption DER, the process is the same, with the exception of the replacement of the existing meter with a bidirectional meter, as there is no excess energy that will be exported to the grid.
To find out more about DER, call our business hotline: 16210. Applicants can also go to the nearest Business Center or contact Biz and E&N Relationship Managers to inquire about DER.
DER List of Application Requirement
Scroll horizontally to see all columns.
| # | End-user-consumption and Exporting DER | Non-exporting DER |
|---|---|---|
| a. Regular Application Requirements | ||
| 1 | Letter of Intent signed by Authorized Signatory | |
| 2 | Identification Documents; ID for Representatives | |
| 3 | Updated Electrical Plan, duly signed and sealed by the Professional Electrical Engineer (PEE) | |
| 4 | Certificate of Final Electrical Inspection (CFEI) | |
| b. DER Facility Requirements | ||
| 1 | Application Form for Interconnection of DER Facility | |
| 2 | List of Certified Equipment | |
| 3 | Plant Parameters Form (PPF) including Detailed Planning Data | |
| 4 | Fixed Asset Boundary Document (FABD) | |
| 5 | Certificate of Compliance from the ERC (see below) | |
| c. Certificate of Compliance (COC) Filing Requirements | ||
| 1 | Application (COC Form No. 1), as applicable | |
| 2 | Company Profile (COC Form No. 2), as applicable | |
| 3 | Renewable DER Supply Agreement with Distribution Utility (DU) | - |
| 4 | - | Environmental Compliance Certificate, as applicable |
| 5 | DU Certificate that the Renewable DER is technically compliant with the Philippine Distribution Code (PDC) / Philippine Small Grid Guidelines (PSGG) | |
| 6 | Permit to Operate (PTO) issued by the Department of Environment and Natural Resources (DENR), as applicable | |
| 7 | Management and/or lease contracts in force (in case the DER is operated, leased and/or managed by an entity other than the End-User/Owner), if applicable | - |
DER Benefits for Businesses
A customer availing of the DER program, whether for its own use and export or own use only, will reduce its dependence on grid power, hence, will benefit from the lower cost of electricity generated by its DER facilities for his own consumption. Moreover, if the energy generation of the DER facility is more than the customer’s requirements, the excess is exported to the grid if it is enrolled to both the own-use and exporting DER program.
When a customer avails of the End-User’s and exporting Distributed Energy (DER) program, Meralco will install in the customer's premises a bi-directional meter that will measure the energy consumed (import) and the energy supplied (export) by the customer to the distribution grid. Meralco will likewise install a REC (Renewable Energy Certificate) meter that will measure the gross electricity production from the RE system.
For a business with photovoltaic (PV) energy source, when there is sunshine during the day, the solar facility is intended to supply a portion of the energy needs of the customer while any excess energy will be exported to the grid. Per DER Rules, exported energy from a maximum of 30% of the nameplate capacity of an RE system will be compensated, allowing the business to recover from its renewable investment faster while helping boost overall energy supply into the grid. At times when there is no sunlight, or at night, the grid will provide electricity to supply the customer’s full power requirements. Exported and imported energy are measured by the bi-directional meter.
The REC meter will measure energy generation from RE-based facilities under DER. Such generation will be entitled to RECs, upon registration of the facility with the RE Market. RECs may be sold to other RE Market participants.
To get the total electric bill, the value of the energy exported by the customer will be subtracted from the value of the imported energy from Meralco. On the other hand, for a customer enrolled in the DER for End-User’s consumption only, the total electric bill shall be the amount computed corresponding to the much lower import consumption.
Aside from the compensation provided by the DER Rules to the excess energy exported by RE systems, applying for DER ensures that the RE installation is compatible with the power grid and complies with interconnection standards for safe and reliable operations. Registration of DER with Meralco will also enable customers to earn RECs, which may be sold to other RE Market participants.
On a national level, participation in DER aids in the development of RE resources to reduce dependence on imported fossil fuels and assists in the thrust for more sustainable sources of energy.
Safety Benefits of Registering RE Installations with Meralco
If Meralco is unaware that you have an RE installation, you put yourself and others at the risk of:
- Inaccurate billing
- Electrical fires
- Neighborhood blackouts
- Damage to motors and electrical equipment
- Grid instability
- Service interruption
- Electrocution of power utility personnel
In addition to these, the ERC requires securing a COC prior to the operation of a renewable DER facility. And, registration of DER with Meralco will also enable you to earn RECs, which may be sold to other RE Market participants.
Hosting Capacity for DER
For DER Applications requesting for connection to Meralco’s feeders with primary voltages of 13.8 kV or 34.5 kV, determination of available hosting capacities is subject to current loading of the feeder including the distribution transformer and existing embedded generating facilities connected to it. Thus, a Distribution Impact Study (DIS) must be conducted to evaluate the impact of a DER application before it can be allowed to connect to any Meralco feeder as prescribed in the DER Rules and the latest Philippine Distribution Code.
For initial reference, but subject to the conduct of the DIS, the total aggregate capacity of embedded generators allowed for interconnection to Meralco’s distribution system should not exceed 8 MW and 3 MW for feeders operating at 34.5 kV and 13.8 kV, respectively.
DER Distribution Impact Study (DIS) and Distribution Asset Study (DAS) Fees
Scroll horizontally to see all columns.
| Study | Distribution Impact Study (DIS) |
|---|---|
| Rationale | The DIS assesses the ability of the Distribution System to safely and reliably accommodate a proposed Connection Agreement and any upgrades that may be required. |
| Type & Fees* | Type 1: <5kW (Php 1,900) Type 2: 5kW to 100kW (Php 17,700) Type 3: 101kW to 200kW (Php 30,000) Type 4: 201kW to 999kW (Php 40,000) Type 5: >=1MW (Php 70,000) *NOTE: For exporting DER, no fees shall be imposed on the conduct of the DIS |
| Assessment (as needed) | Technical Impact Study / Field Verification / Systems Parameter Measurements |
| Inclusive of (as needed) | 1. Circuit modelling 2. Load flow and short circuit analysis 3. Voltage study 4. Verification of penetration limits 5. Field verification of existing secondary distribution 6. Load profiling 7. Measurement of baseline system and power quality parameters 8. Verification of thermal loading and voltages |
| Description | Meralco simulates the proposed RE installation to the customer's load and its impact to the grid. This is to determine if the proposed RE installation will be safe to the customer and neighboring grid, or if additional facilities are needed. The simulations are performed off-line and do no cause interruption to the customer's use of electricity. |
Scroll horizontally to see all columns.
| Study | Distribution Asset Study (DAS) |
|---|---|
| Rationale | The DAS will determine all distribution assets and costs necessary to accommodate a proposed interconnection. |
| Type & Fees | Depending on the DIS Result if needed. Cost is variable depending on the capacity and complexity of the project. |